November 2024: Work on a terrace drain will take up much of the early part of the month. An existing driveway will be removed and replaced with a new driveway later in the month and into December. A pedestrian walkway along the north side of Portola will be rerouted to accommodate that construction, using K-rail for safety.
October 2024: Construction of the wall rimming the roadway will be completed early in the month, to be followed by curb and gutter work.
September 2024: Work will continue on the wall rimming the roadway early in the month, then move to the driveway apron for the new road, at which time the pedestrian detour will be reopened for safety.
August 2024: Construction crews will remove plant material from parkway and center median areas affected by upcoming construction. A temporary walkway will be established along the north side of Portola Parkway to allow for work to take place within the existing sidewalk area for storm drains and a driveway apron for the new road. The pedestrian detour will be rerouted for a few weeks to the area of the original sidewalk early in the week of Aug. 26.
July 2024: Construction crews will continue work on the wall rimming the driveway. Toward the end of the month, work will begin to prepare for a temporary walkway to be used by pedestrians during construction of the project.
June 2024: Work will be focused this month on the wall that will rim the edge of the driveway. This will include installation of rebar, placement of shotcrete, footings, and more.
May 2024: Storm drain construction will continue into the middle of this month to complete work for two additional storm drain lines. This will include excavation, laying of pipeline, and backfilling, along with other construction.
April 2024: Storm drain construction will continue this month, including removal of a v-ditch, road excavation, digging and backfilling, and other construction.
March 2024: Work will begin the week of March 11 to clear and grub the site to make way for construction later this month, beginning with storm drain work.
February 2024: Work will begin this month to install temporary fencing and temporary erosion control for the project.